Project Timeline Update

As the Centennial Airport Part 150 Noise Compatibility Study continues to progress, we wanted to share an update on the project timeline. Over the past several months, the Study Team has been modeling, analyzing, and vetting potential operational, land use, and facility measures for inclusion in the Draft Noise Compatibility Program (NCP) with the Study Advisory Committee (SAC). We will meet with the SAC and Roundtable again later this summer (2026) to finalize the measures that will comprise the Draft NCP. We will then publish the Draft NCP for public review and comment and hold a public hearing. This is anticipated to occur in the Fall of 2026. Following the public review and comment period, the Study Team will make any needed revisions to the NCP and submit it before the end of the 2026 calendar year to the FAA for its approval or disapproval of the NCP measures.